A Typical Project



Industrial ] Vivier Explained ] Marine ] [Conversions] Contact Us ] Home ]


This page gives you an idea of the work involved to produce a SSWS vivier lorry system

Click here to contact us by clicking this button Call Now

Vivier Lorry

Day 1
Front Exterior
 

Layout and design phase is expected to take approximately 2 weeks.
Templating, electrical/pipework routing and first fix approximately 2 weeks.
Final fit, testing, implementation and acceptance trial will be the final phase of the project and should take approximately 7-10 days.

 

Click here to contact us by clicking this button Call Now

Day 1
Back Exterior

        Click here to contact us by clicking this button Call Now

Day 1
Interior

Day 16
Interior and blowers

Day 21
Interiors (Tank Framing in Place)


Vivier Lorry Internals

Day 28

Interiors and Exteriors secondary glassing

Click here to contact us by clicking this button Call Now

 

Day 30
Interior: Bays and walkway

Vivier Tanks

 

Day 36
Installed pipework and drains.


Day 36
Blower Cradle Preps.

 

Click here to contact us by clicking this button Call Now

Drains and pipeline feeds in place.
Final stages of completing the wiring,
control systems and blowers installation on
the external cradle.

 

 